Operations Center Status

Exterior framing and interior studding are essentially complete and the building is being weatherproofed with exterior sheeting and roofing. Until the windows are delivered, the building will be completely sealed with exterior material. Also completed is the surface water runoff system which closes the hole in the back of the property. The vault was delivered and installed at the beginning of December. Utilities accounts for the property are being established and the electrical and plumbing work is just now beginning. The projected completion date for the building continues to be April 20, 2018.Render of Operations Center Front View